Item P.1
Contract with RDH Building Science for Craneway Pavilion Condition Assessment
Hire building experts to assess Craneway Pavilion condition for $169,500
Item P.1
Contract with RDH Building Science for Craneway Pavilion Condition Assessment
Contract with RDH Building Science for Craneway Pavilion condition assessment
Tuesday, August 19, 2025
Tuesday, June 24, 2025
Item T.4.a
Resolution to Contract for 2025 Dredging at Terminal 2, Berth’s 7 and 8 of Point Potrero Marine Terminal, and the Marina Bay Yacht Harbor
Authorize $5.8 million contract for dredging at port terminals and Marina Bay
Item V.2
Approval of Engineer’s Report and Intent to Levy Assessments for Marina Bay Landscape and Lighting Maintenance District (MBLLMD) for Fiscal Year (FY) 2025-2026
Increase property assessments by 3% for Marina Bay landscaping and lighting
Tuesday, May 27, 2025
Tuesday, March 25, 2025
Tuesday, February 25, 2025
Tuesday, July 2, 2024
Monday, June 24, 2024
Item W.9.c
Marina Bay Parkway Force Main Relocation Project Completion
Accept Marina Bay sewer line replacement project as complete and pay $356,786 cost overrun
Item L.2
Rental Assistance Demonstration (RAD) Program Application for Richmond Village.
Apply for federal program to convert Richmond Village public housing subsidies
Tuesday, June 18, 2024
Item L.2
Rental Assistance Demonstration (RAD) Program Application for Richmond Village
Authorize housing authority to apply for federal program to improve Richmond Village funding
Item W.9.c
Marina Bay Parkway Force Main Relocation Project Completion
Accept $790,050 sewer pipe replacement project as complete
Item L.2
Rental Assistance Demonstration (RAD) Program Application for Richmond Village.
Authorize housing authority to apply for federal funding to renovate Richmond Village
Tuesday, March 26, 2024
Tuesday, February 20, 2024
Tuesday, June 20, 2023
Tuesday, May 2, 2023
Tuesday, December 6, 2022
Tuesday, June 15, 2021
Tuesday, June 1, 2021
Tuesday, June 16, 2020
Tuesday, May 5, 2020
Tuesday, February 18, 2020
Tuesday, June 18, 2019
Tuesday, June 4, 2019
Tuesday, May 21, 2019
Tuesday, May 7, 2019
Tuesday, June 19, 2018
Item H-2
Contract with McNabb Construction for trash enclosure
Hire McNabb Construction to build $325,000 trash enclosure at Melville Square
Item K-2
Marina Bay Landscaping and Lighting Maintenance District assessment levy
Approve 3% increase in Marina Bay landscaping and lighting assessments
Tuesday, May 15, 2018
Tuesday, May 1, 2018
Tuesday, March 27, 2018
Tuesday, June 20, 2017
Item J-2
Marina Bay Landscaping and Lighting Maintenance District assessments
Approve 3% increase in Marina Bay property assessments for landscaping and lighting
Item H-16
Agreement with Manson Construction Co. for dredging
Hire Manson Construction to dredge harbor channels for $1.9 million
Tuesday, May 16, 2017
Tuesday, February 7, 2017
Tuesday, January 17, 2017
Tuesday, June 7, 2016
Tuesday, May 3, 2016
Tuesday, April 19, 2016
Tuesday, July 21, 2015
Tuesday, May 5, 2015
Tuesday, February 17, 2015
Tuesday, February 3, 2015
Tuesday, September 16, 2014
Tuesday, June 3, 2014
Tuesday, May 6, 2014
Tuesday, March 18, 2014
Item G-10
Marina Bay Landscape & Lighting Maintenance District budget amendment
Amend Marina Bay Landscape & Lighting Maintenance District budget
Item G-3
Resolution ordering preparation of Engineer's Report for Marina Bay Landscape and Lighting Maintenance District
Order preparation of annual cost report for Marina Bay landscaping district
Tuesday, December 17, 2013
Tuesday, July 30, 2013
Tuesday, June 4, 2013
Tuesday, May 21, 2013
Tuesday, April 23, 2013
Tuesday, March 19, 2013
Tuesday, February 5, 2013
Item SA-1
Public Highway Underpass Crossing Agreement
Execute agreement for railroad underpass crossing at Marina Bay Parkway
Item J-4
Marina Bay Landscape and Lighting Maintenance District Engineer's Report
Order preparation of engineer's report for Marina Bay landscaping district costs
Tuesday, December 4, 2012
Tuesday, September 11, 2012
Item L-4
Reconsideration of Cosco Busan oil spill settlement allocation
Reallocate $669,000 from 2007 oil spill settlement to Marina Bay Trail repairs
Item L-3
Salt Water Construction contractual compliance report
Receive report on Salt Water Construction's contract compliance for harbor dredging
Tuesday, July 24, 2012
Tuesday, June 5, 2012
Tuesday, May 1, 2012
Tuesday, October 4, 2011
Tuesday, July 19, 2011
Tuesday, June 21, 2011
Tuesday, May 3, 2011
Tuesday, January 4, 2011
Tuesday, July 20, 2010
Tuesday, June 1, 2010
Tuesday, May 18, 2010
Tuesday, March 2, 2010
Item G-1
Contract with Willdan Financial Services for Landscape Maintenance District administration
Hire Willdan Financial Services to manage 2 landscape maintenance districts for $14,500
Item G-3
Resolution ordering Engineer's Report for Marina Bay Landscape and Lighting Maintenance District
Order engineer's report for Marina Bay maintenance district costs and improvements