Accept Marina Bay sewer line replacement project as complete and pay $356,786 cost overrun
In Plain English
The city replaced 2 underground sewer lines in Marina Bay in 2021 to reduce sewage overflows. Workers discovered a broken manhole with no bottom and 3 unmapped sewer connections during construction. If approved, the city pays $356,786 in additional costs and officially closes the project.
Auto-generated summary. Source: official agenda documents.
Related Items
Accept 2024 slurry seal street project as complete
Mar 24, 2026
Hire SCI Consulting Group for $70,000 to analyze funding for fire services and pavilion operations
Feb 17, 2026
Hire building experts to assess Craneway Pavilion condition for $169,500
Dec 2, 2025
Contract with RDH Building Science for Craneway Pavilion condition assessment
Dec 2, 2025
Direct city staff to plan major upgrades to Cheese Park including permanent restrooms and playground safety improvements
Mar 24, 2026
Accept Ferry Point sewer pump station upgrade as complete
Mar 17, 2026
Direct staff to plan comprehensive improvements at Cheese Park including restrooms and safety upgrades
Mar 17, 2026
Direct staff to plan major improvements at Cheese Park including restrooms and playground upgrades
Mar 3, 2026
Bicycle Circulation Modifications near West Cutting Boulevard and South Garrard Boulevard
Jan 27, 2026
Approve $419,748 for bike path changes, intersection improvements, and slope mowers
Jan 27, 2026