Award emergency contract to repair high-voltage equipment at Port facilities
$89,870
Resolution <UNKNOWN>
In Plain English
Critical electrical equipment at Port facilities failed and needs immediate repair. The Port cannot operate safely without functioning high-voltage systems. Bass Electric will fix the equipment and provide temporary power during repairs for $89,870.
Auto-generated summary. Source: official agenda documents.
Votes
Approve consent calendar
PassedCommunity Discussion
This discussion was submitted to the City Clerk as part of the public record.
Comments are submitted to the Richmond City Clerk before the meeting. By commenting, you agree to have your name and comment included in the public record.
Similar Discussions
5 related items found by meaning
Approve emergency contract with Bass Electric for port electrical repairs
Hire Rosendin Electric for $80,000 emergency repairs at Red Oak Victory Ship and Point Potrero Marine Terminal
Approve emergency $16,000 contract for high voltage power line repair
Award $228,000 emergency contract to build temporary dock structures at Terminal 2
Hire 3 electrical contractors to maintain aging Port of Richmond infrastructure
The Story So Far
Related items from other meetings
Hire law firm for general legal advice and lawsuits
Update sidewalk vendor permit rules and enforcement procedures
Hire Bennett Gelini law firm for litigation and liability claims through 2028
Hire consulting firm to study Port of Richmond's economic impact
Approve 3-year contract with Unity Courier for library book delivery service
Update administrative procedures and enforcement for sidewalk vendors
Approve $299,797 contract to plan relocation of historic SS Red Oak Victory ship
Extend LCP Tracker labor compliance software contract by $29,000 through 2027
Increase Pogo Park contract by $3.3 million to complete Harbour-8 Park expansion
Hire consultant to help find new operator for water treatment and storm systems