Accept completed playground renovation at Shields-Reid Park
$161,070
In Plain English
McNabb Construction finished renovating the playground at Shields-Reid Park on August 2, 2007. The project cost $161,070 and updated play equipment and safety features. If approved, the city formally accepts the completed work and can release final payment to the contractor.
Auto-generated summary. Source: official agenda documents.
Votes
Approve consent calendar
8 to 0
Similar Discussions
5 related items found by meaning
Award $157,500 contract to renovate play equipment at Shields-Reid Park
Hire McNabb Construction to move playground equipment from Elm Play Lot to Lucas Park
Award $4.1 million contract to renovate Shields-Reid Park in North Richmond
Add $400,000 to Shields-Reid Park construction contract for community center maintenance
Award contract to improve drainage and landscaping at Shields-Reid Park
The Story So Far
10 prior discussions on this topic
Contract with Oldcastle Infrastructure, Inc. for Hydrodynamic Separator Maintenance Services
NEMA Construction contract for Traffic Calming
Construction Agreement Amendment No. 1 with Bauman Landscape and Construction, Inc. for the Boorman Park Revitalization Project
Roadway Modification at Glenn Avenue and McBryde Avenue for the McBryde Avenue Safe Routes to Park Project
Ordinance Modifying Chapter 12.19 of the Richmond Municipal Code entitled “Onsite Wastewater Treatment Systems.”)
Contracts with CoroData Records Management and Iron Mountain, Inc. to Provide Off-site Records Storage and Retrieval Services
Contract with NBS Government Finance Group for an Independent Fiscal Analysis of the Public Safety Funding and Minimum Police Staffing Charter Amendment
Proclamation Honoring the Life and Legacy of Joe Lee Fisher Sr.
Side Letter with Richmond Police Management Association Regarding Special Compensation Practices
Zoning Text Amendments Related to Accessory Dwelling Units and Junior Accessory Dwelling Units