Add $120,000 to Point Potrero Marine Terminal pavement repair contract

Police & Community SafetyContracts

In Plain English

The city originally approved $287,000 for pavement repairs at Point Potrero Marine Terminal in April. The contractor discovered additional work needed including traffic barriers to reduce illegal activities, pipe repairs in historic ship basins, and fire water line replacement for the Red Oak Victory ship. Adding this work now saves money because the contractor is already on site with equipment.

Auto-generated summary. Source: official agenda documents.