Authorize $4.7 million sewer upgrades on Cutting Boulevard and Harbour Way South

Police & Community SafetyContractsPublic Works

$4,715,645

Resolution Resolution No. 117-25

In Plain English

The city must complete this project by June 30, 2026 to comply with a 2018 legal settlement with San Francisco Baykeeper. The work installs 3,700 feet of new 30-inch sewer pipes to prevent overflows during storms. If approved, construction takes 18 months and comes from the wastewater fund.

Auto-generated summary. Source: official agenda documents.

Votes

Approve consent calendar

Moved by: Sue WilsonSeconded by: Cesar Zepeda
Passed

6 to 0

Soheila BanaAye
Claudia JimenezAye
Doria RobinsonAye
Sue WilsonAye
Cesar ZepedaAye
Eduardo MartinezAye
Jamelia BrownAbsent