Increase Turner Group Construction contract by $89,500 for Elm Play Lot renovation

Police & Community SafetyContractsParks and RecreationContract

$1,335,436

In Plain English

The city hired Turner Group Construction to renovate Elm Play Lot and its community building using grant funding. Construction costs rose during the project, requiring additional money. If approved, the total contract increases from $1.2 million to $1.3 million, all covered by grants.

Auto-generated summary. Source: official agenda documents.

Votes

Approve consent calendar