Accept completed 7th Street bike lane project and approve $121,203 cost increase

7th Street Bike LaneInfrastructureResolution

In Plain English

The city installed new bike lanes on 7th Street through contractor Rapid Grading. The project cost more than expected, requiring an additional $121,203 beyond the original contract. If approved, the total project cost rises to $420,039 and the contractor receives final payment.

Auto-generated summary. Source: official agenda documents.

Community Discussion

This discussion was submitted to the City Clerk as part of the public record.

Comments are submitted to the Richmond City Clerk before the meeting. By commenting, you agree to have your name and comment included in the public record.