Pay extra $121,236 to complete 37th Street bike lane project

Police & Community SafetyContracts

In Plain English

The city's bike lane project on 37th Street hit unexpected conditions during construction that required additional signal poles and equipment. The original contract was $804,541 but the final cost is $925,777. If approved, the city pays the remaining balance and officially accepts the completed project.