Award $945,681 construction contract for Wall Avenue storm drain improvements
$945,681
Resolution 18-3
In Plain English
The city selected R.V. Stich Construction to upgrade storm drains along Wall Avenue. The contract includes $859,710 for construction plus $85,971 in contingency funds for unexpected costs. If approved, work begins on infrastructure designed to handle heavy rainfall and reduce flooding.
Auto-generated summary. Source: official agenda documents.
Votes
Approve consent calendar
7 to 0
Similar Discussions
5 related items found by meaning
Approve extra spending for Wall Avenue storm drain construction due to cost overruns
Approve $1.4 million contract for 1st Street sewer system upgrades
Hire contractor to build missing sidewalks on Stege Avenue and fix drainage problems
Approve final $242,036 payment to complete Rheem Creek flood reduction project
Award $189,455 contract to build missing sidewalks on Stege Avenue
The Story So Far
2 prior discussions on this topic
Richmond Government Accountability, Transparency, and Ethics Act (Richmond GATE Act) Placing a Ballot Initiative on the November 2026 Ballot to Adopt an Ordinance that Establishes an Independent Ethics Commission
Richmond Government Accountability, Transparency, and Ethics Act (Richmond GATE Act) Placing a Ballot Initiative on the November 2026 Ballot to Adopt an Ordinance that Establishes an Independent Ethics Commission
Related by category
Extend recruitment contract for specialized city positions
Review city study and project timelines for coordination
Upgrade marine terminal lights to LED
Approve $144,000 contract for e-discovery software
Approve off-site records storage contracts with two vendors
Hire Jason Corburn for neighborhood safety data services
Approve $52,525 contract to maintain BikeLink lockers
Hire Danny Walker to officiate city sports programs