Hire Schaaf & Wheeler to complete Ferry Point Pump Station construction engineering

Police & Community SafetyContracts

$50,000

In Plain English

The city is building a new pump station to replace aging sewer equipment at Ferry Point. Construction is nearly finished but the engineering firm's contract expired on December 31, 2023. If approved, Schaaf & Wheeler continues as the project engineer through January 2025 for $50,000 from the wastewater fund.

Auto-generated summary. Source: official agenda documents.

Votes

Approve consent calendar

Moved by: Councilmember ZepedaSeconded by: Councilmember Willis
Passed