Increase R3 Consulting Group contract by $26,884 for permit compliance review

Police & Community SafetyContracts

$102,884

In Plain English

The city hired R3 Consulting Group to help review whether the Bulk Materials Processing Center follows its operating permit conditions. This facility requires a 5-year compliance check. The contract started at $76,000 but needs an additional $26,884 to complete the work, bringing the total to $102,884.

Auto-generated summary. Source: official agenda documents.

Votes

Approve consent calendar

Moved by: Eduardo MartinezSeconded by: Demnlus Johnson III
Passed

7 to 0

Thomas K. ButtAye
Nathaniel BatesAye
Ben ChoiAye
Demnlus Johnson IIIAye
Eduardo MartinezAye
Jael MyrickAye