Increase wastewater treatment plant upgrade budget by $3.5 million to $45.6 million

Wastewater Treatment PlantContracts

In Plain English

The city is replacing aging grit removal and aeration systems at the Richmond Wastewater Treatment Plant to improve efficiency and meet future regulations. Change orders for unforeseen issues have nearly exhausted the original contingency budget. If approved, the total project cost rises from $42.1 million to $45.6 million, funded by a $50 million state loan.