Increase Ghilotti Bros construction contract by $700,000 for Richmond Wellness Trail Phase I

Police & Community SafetyContractsContract

$700,000 increase, total $1,000,000

Resolution 154-21

In Plain English

The city awarded Ghilotti Bros a contract to build the first phase of the Richmond Wellness Trail. Construction costs have risen from the original $300,000 to $1 million total. If approved, the additional $700,000 covers unexpected expenses during trail construction.

Auto-generated summary. Source: official agenda documents.

Votes

Approve consent calendar